SNHU Kingston Hall Exhaust Modifications

Southern New Hampshire University · Manchester, NH · 2026

Kingston Hall stayed open all summer. We modified the bathroom exhaust system of the 106,000 square foot residence hall one wing at a time, with our own crews on the work and residents in the building throughout.

SNHU Kingston Hall, Southern New Hampshire University, Manchester, NH

The project

Southern New Hampshire University needed Kingston Hall’s bathroom exhaust system modified between April and August 2026, with summer residents in the building. The scope covered duct cleaning floor by floor, new exhaust fan motors and new access panels.

How we did it

Working closely with the university, we flipped summer occupants from one wing to the other as the work advanced, keeping zero-downtime occupancy through the university’s summer academic calendar.

We ran the work in MS Project and Procore, with visual aids and signage in the spaces, so each area went back to the university as soon as its exhaust system was turned back on.

Phase 2 logistics plan, April 2026. Opens the full-size drawing.

Client
Southern New Hampshire University
Location
Manchester, NH
Size
106,000 GSF
Schedule
April to August 2026
Conditions
Phased, occupied building
Services
Construction management
Self-perform general contracting
Scheduling
User group coordination